THE ITC

BUILDING REWIRING PROJECT


Table of Completed/Pending Buildings


Information Updated as of 10/27/98
(for more detailed information, email to itc-rewire@Virginia.EDU)
BUILDING
NAME

CURRENT
STATUS

INITIAL
MEETING

APPROVAL
DATE

START
DATE

COMPLETION
DATE or % Finished

Aerospace Research Lab (rles)completed5/13/96-4/8/9710/7/97
Alderman Librarycompleted5/24/96-7/21/972/27/98
Bayly Museumcompleted3/19/964/30/9611/1/9611/30/96
Bemiss Housecompleted---4/1/98
Booker Housecompleted3/13/964/30/966/4/967/1/96
Brooks Hallcompleted3/28/965/2/968/13/961/7/97
Bryant Hallbuilding being removed3/21/965/24/96-skip
Buckingham Cottagecomplete6/18/961/10/97-2/24/98
Cabell Hall (New)done4/30/9611/5/961/27/975/2/97
Cabell Hall (Old)done5/14/9611/25/962/3/975/2/97
Cafe Northcompleted3/19/965/24/9612/23/9612/23/96
Campbell Hallcompleted3/1/967/24/968/12/961/1/97
Carr's Hillcompleted6/18/961/10/972/20/972/24/98
Carruthers Hallhold - renovation - many parts done8/13/96---
Carruthers Hall - Auditcompleted8/13/96-4/22/976/3/97
Carruthers Hall - Purchasingcompleted---6/9/98
Computer-Aided Engineeringcompleted7/23/962/24/975/23/978/19/97
Chemical Engineeringrework completed-1/6/981/12/985/7/98
Chemistyhas UTP - needs upgrade4/7/98---
Clark Hallhold - per department request5/30/96---
Clark Hall Librarycompleted12/963/3/983/10/988/25/98
Clemons Librarycompleted-3/01/963/05/965/02/96
Cobb Hallcompleted2/13/966/30/967/10/9612/9/96
Cocke Halldone---7/1/94
Cresap Road (108)completed---completed
Culbreth Helms Theatrecompleted3/22/965/20/968/19/961/7/97
Darden Schooldone---Completed
Dawson's Rowdone--2/01/962/27/96
Env Sci Machine Shopdone---7/21/97
Faulkner House (Miller Center)completed6/12/967/22/968/15/969/15/96
Fayerweather Hallcompleted2/1/964/30/9610/1/9611/11/96
Fiske Kimball Librarywork in process 3/20/9610/9/961/13/973/3/97
Forestrydone--7/12/957/21/95
Garrett Hallcompleted-2/3/972/20/976/10/97
Gilmer Hallcompleted4/30/96-8/25/976/09/98
Halsey Halldone-3/15/95-4/11/95
Health Sciences Librarycompleted8/7/9612/15/961/1/974/8/97
Heat Chiller Plantcompleted6/7/966/12/965/12/9710/28/97
High Energy Physics Labdone-2/8/962/21/964/1/96
Housing Officesin progress--10/27/98-
International Centerdone4/1/968/2/9611/23/961/20/97
Jordan Hall (New)done during construction---done
Jordan Hall (Old)Completed2/13/96-2/25/973/10/98
KCRCMCC Building--4/29/976/24/97
Lambeth Housedone-3/6/964/16/966/1/96
Law Schoolrenovation--9/1/969/5/97
Leake (Facilities Management)done-5/2/965/17/967/1/96
Levering Hallhistorical building issues-6/10/97--
Luther Jackson Housedone--2/1/962/27/96
Madison HallCompleted6/18/961/10/976/30/977/28/97
Madison Housein progress--4/1/9830%
Material Handling Facilitydone11/2/94-2/1/954/1/95
Material Sciencedone11/28/94-4/12/955/15/95
Math/Astronomydone--7/25/953/26/96
Maury Hallcompleted-7/12/967/12/968/1/96
McCormick Observatorycompleted4/22/965/31/9611/12/9612/15/96
McCue Centerdone-3/25/964/19/967/1/96
McCue Center - new 3rd floordone---9/8/97
McKim Hallcompleted-1/20/981/26/984/15/98
McLeod Hallcompleted6/13/966/26/966/28/9612/2/96
Medical Research #4Completed2/13/968/1/967/25/962/11/97
Memorial Gymnasiumdone2/1/963/8/963/14/966/15/96
Mechanical Engineeringcompleted11/28/942/24/975/6/978/19/97
Mechanical Engineering Trailerscompleted---8/11/98
Michie Bldg Northrework completed---6/9/98
Michie Bldg Southcompleted-9/29/9710/21/972/3/98
Miller Halldone--1/31/953/1/95
Minor Halldone---7/1/94
Monroe Hallcompleted6/14/9611/25/9612/17/961/30/97
Multistorywiring by group---50%
Newcomb Halldone during renovation---9/1/97
North Grounds Heating Plantcompleted6/7/966/12/9610/1/9610/15/96
North Grounds Recreationcompleted2/1/962/15/964/9/9610/1/96
O-Hill Dining Facilitycompleted4/29/965/24/966/15/969/1/96
Olsson Hallwiring complete7/23/966/976/30/9711/11/97
Old Physicsdone--9/1/951/15/96
Outdoor Recreationcompleted2/1/962/15/962/26/968/12/96
Onesty HallCompleted5/15/966/5/9610/18/962/3/97
Parking & Transportationdone---Completed
Peabody Hallcompleted-12/1/9512/13/9512/30/96
Peyton Housedone-11/20/9512/1/952/27/96
Police Stationdone---7/1/94
Primary Care Centercompleted--6/26/971/20/98
Printing & Copying Servicescompleted3/28/964/16/965/17/967/1/96
Randall Halldone---Completed
Reactor Facilityhas UTP - hold possible shutdown----
The Rotundadone---Completed
Rouss HallDone3/25/967/17/967/3/961/28/97
Ruffner Hallcompleted3/6/967/9/962/25/9710/21/97
Rugby Faculty Apartmentscompleted---9/5/97
Slaughter Recreationdone2/1/962/15/963/26/964/22/96
Sponsors Halldone---Completed
Stacey Hallcompleted--10/7/972/24/98
Student Activities BldgCompleted4/29/966/28/965/9/975/9/97
Student Healthhold upgrade for renovation project----
Thornton Hall A-wingcompleted7/23/965/01/977/29/972/3/98
Thornton Hall B&D wingscompleted7/23/96-8/1/971/16/98
Thornton Hall C&E wingsdone7/23/962/24/973/21/975/2/97
University Halldone5/15/9612/15/961/1/975/1/97
University Hospital - 0-Centercompleted-2/6/984/1/988/11/98
University Hospital - 0-Bustlecompleted-2/6/983/3/985/5/98
University Hospital - 2-Westin progress--8/4/98-
University Hospital - 8-Westin progress--10/27/98-
University Hospital - 2-Bustlein progress--10/27/98-
University Hospital West - Berringer Wingdesign in progress----
University Hospital West - Davis Wingdesign in progress----
Varsity Halldone--2/22/953/28/95
Washington Halldone---7/1/94
Wilson Halldone---8/21/96
Zehmer Hallcompleted3/29/967/15/962/11/974/9/97
Zehmer Hall Annexcompleted3/29/967/16/9610/1/9611/5/96
104 Emmet Streetcompleted--10/1/965/2/97

In general, no new network outlets are active or available for use until the work in a building is 100% completed.

| Home Page | Project Specifics | Benefits | Completed/Pending Buildings | FAQ's | Cost |
| Documentation and Wiring Options | Related Info | Contact ITC about Project |

This page maintained by: jaj@Virginia.EDU
This page was last updated: 10/27/98

© 2008 by the Rector and Visitors of the University of Virginia.

The information contained on the University of Virginia’s Department of Information Technology and Communication (ITC) website is provided as a public service with the understanding that ITC makes no representations or warranties, either expressed or implied, concerning the accuracy, completeness, reliability or suitability of the information, including warrantees of title, non-infringement of copyright or patent rights of others. These pages are expected to represent the University of Virginia community and the State of Virginia in a professional manner in accordance with the University of Virginia’s Computing Policies.